Expansion Timeline
Stay up to date on the latest developments and milestones as we build and enhance the GISB facilities for our community.
Fall 2025
Welcome Back!
Students return to two freshly updated buildings!
Summer 2025
Renovation Ramps Up at Both Buildings
- UC Renovations underway
- Finish interior renovations and gym floor at LC
- Assemble and install furniture at LC & UC
- Move in!
Spring 2025
Renovation Underway
- Paint
- Refinish Floors
- Update built-in furniture
- Order new furniture
Winter 2024/2025
Construction
- Start of Construction/Renovation at Belmont Street
- Start of Pre-Construction at Holton Street
Fall 2024
Tasks and Activities:
- Finalize Architectural Plans and Budget
- Secure Building Permits
- Start Pre-Construction at Belmont Street
August 2024
Hired Timberline Construction Company
Summer 2024
Tasks and Activities:
- Develop Architectural Plans and Budget
- Interview and Hire Construction Manager and Construction Company
May 2024
Third Site-visit with German School Building Consultant from gpe-Projekt and approval of Design Concept
Planning Meeting with Design Team, Architects and Engineers
Membership Meeting
March 2024
Site Evaluation of the Holton Street and Belmont Street Properties
3D scans of both facilities for virtual models of GISB
February 2024
Board of Trustees hires Behnisch Architekten as Architect of Record
January 2024
Second site-visit with German School Building Consultant from gpe-Projekt
November 2023
New Campus Leases Secured
May 2023
First site-visit with German School Building Consultant from gpe-Projekt
April 2023
Hired gpe-Projekt as German Building Consultant
March 2023
Hired Owner’s Project Manager from JLL
2023
Contract negotiations with landlord for Holton St Extension and Belmont St Lease