We’re excited to share the latest updates on our renovation projects at both the Belmont Street and Holton Street campuses. As we get closer to the start of the school year, each space is coming together beautifully—see more images of the progress in our Bildergalerie.

Belmont Street: Almost There!
We’re nearing the finish line at Belmont! Most of the painting is complete, with just a few smaller rooms and final touch-ups left to go. All materials and classroom supplies have been moved over from Holton Street, and now we’re focused on the finishing touches.
Next up: cleaning, HVAC maintenance, window washing, and landscaping. The kitchen is well underway—appliances have been ordered and are expected to arrive next week. Once installed, we’ll be able to wrap up the kitchen renovation quickly. Meanwhile, tiling in the final two bathrooms is in progress, and work on the gym floors is nearly complete, featuring Bruno the Bobcat! We’re also planning to install the new outdoor fence within the next two weeks, weather permitting.

Holton Street: Work in Progress
Renovation efforts are ramping up at Holton Street. Painters are already on site, and demolition work has begun. Last week, crews started on the teacher lounge and cafeteria. This week will bring the demolition of the old fallout shelter in the Physics classroom and the installation of new steel support beams—a process expected to take about four days.
Classroom improvements are moving forward as well, with floor replacements and fresh paint underway. While earlier delays have set us back slightly, we anticipate some painting will continue into August.
We’re expecting additional furniture deliveries by the end of the month. Around that time, we’ll also begin the major move—shifting materials and classroom setups from Belmont Street and Western Avenue to Holton Street. Our goal is to have rooms cleaned, furnished, and ready for staff and students shortly after.
Looking Ahead: A New Partnership with Star Academy
We’re also pleased to announce a new collaboration with Star Academy, a Russian immersion school serving preschool through third grade. We’ve signed a Memorandum of Understanding (MOU) that outlines how we’ll share space and work together in the coming year.
With similar age groups and educational goals, our two schools are well-aligned. We’ve already toured each other’s campuses, and we’re excited about the opportunities this partnership brings for collaboration and community-building.
We’ll continue to share updates as we move closer to completion. Thank you for your ongoing support and enthusiasm—this transformation wouldn’t be possible without our amazing school community!